Wisconsin Street and 35th Street Complete Reconstruction:

The City began work on the reconstruction/overlay of Wisconsin Street from 15th Street west just past PVJH and also 35th Street from Wisconsin Street to Valley Drive.  Check out the "In the Works" page for more updates, timetables, road closures, etc...   This major project will include culvert replacement, tearing out and replacing/overlaying the existing road surface, and work on a sidewalk/walkway on the north side of Wisconsin Street. This will be a major project, with many moving parts - so watch for added information on staging of the project, temporary road closures and detours, construction equipment and barricades. The City has been and will continue to work with Pleasant Valley Community School District on the logistics of travel throughout this project. As mentioned - Utility work has already been completed, Culvert replacement work and grading began fall, 2021 and will start up again early spring, 2022.  35th Street and Wisconsin Street roundabout construction will begin this summer.  Thank you for your patience through this much needed improvement in our community! Watch this page for ongoing updates and pictures.

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
Territorial Road Bridge Replacement (x 2):  
The City will be contracting the work for the total replacement of both the Territorial Road Bridge at 277th Avenue and the Territorial Road Bridge just to the east of 277th Avenue across from the Rock Quarry for 2022.  Watch for more information about DETOURS, timetable, and other construction details in the months ahead.

Tentative Timetable:
East Bridge Replacement (by the Rock Quarry):  March 2022 to June 2022.

West Bridge Replacement (by 277th Avenue):  June 2022 to September 2022.


  1. 1
  2. 2
  3. 3
  4. 4
Downtown/Cody Road Sidewalk Replacement/Improvement between May Street and Holland Street:

There will be a number of sections of downtown sidewalk, decorative brick, and handicap egress areas that will be replaced.  Watch for details on Iowa DOT timetable, plans, access during construction, etc... as this project develops.

Tentative Timetable:  June 2022 to September 2022.
  1. 1
  2. 2
Downtown/Cody Road Highway Repair and Resurfacing between May Street and Holland Street:

Highway 67 through Downtown LeClaire will be repaired and resurfaced/overlayed  in 2022.  Watch for additional Iowa DOT plans and construction timetable as this project gets closer. 

Tentative Timetable:  June 2022 to September 2022.  (Note:  Resurfacing/overlaying will most likely not be started until the sidewalk/decorative pavement replacement is completed.